    摘要:

    根据工程建设的需要,为了全面验证枢纽建筑物整体布置方案的合理性,对江西信江八字嘴枢纽工程进行了整体水工模型试验。通过模型试验研究其水力特性和流态,在满足消能防冲的条件下,创造安全的通航水流条件,确定了枢纽整体布置形式和消能工体型。试验成果优化了枢纽建筑物布置方案,为工程设计提供了技术依据。

    Abstract:

    According to the needs of the project construction, in order to fully verify the rationality of the overall layout plan of the hub buildings, the overall hydraulic model test for the Bazizui hub project in Xinjiang river of Jiangxi province was carried out.The hydraulic characteristics and flow patterns are studied through the model test, and the safe navigable flow conditions are created under the conditions of energy dissipation and erosion prevention.Meanwhile,the overall layout of the hub and the shape of the energy dissipator are determined.The test results provide an optimized layout plan for the hub buildings and provide a technical basis for engineering design.

    参考文献
    相似文献
    引证文献
引用本文

涂晓霞,刘博文.信江八字嘴枢纽工程整体水工模型试验研究[J].江西水利科技,2024,(1):

复制
分享
文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:
  • 最后修改日期:
  • 录用日期:
  • 在线发布日期: 2024-03-21
  • 出版日期:
文章二维码