    针对某水库土石坝渗漏问题采用了“黏土斜墙+贴坡排水”的加固方案.本文对加固前后土石坝稳定渗流期和非稳定渗流期的坝体渗流及坝坡稳定性进行了分析.结果表明:与加固前相比,土石坝加固后的渗流量及渗透坡降均有所下降,上游坝坡安全系数升高,下游坝坡失稳概率大幅度降低.加固后的坝体稳定安全系数满足规范要求,说明所采用的工程加固措施是有效的、可靠的.

    Abstract:

    Aiming at the seepage of an earth rock dam,reinforcement scheme of inclined clay wall combined with drainage of bank slope is adopted.The seepage and slope stability of the earth rock dam before and after reinforcement are analyzed during stable seepage period and unstable seepage period.The results indicate that compared with earth-rock dam before reinforcement,the seepage discharge and seepage gradient are decreased after reinforcement,the safety factor of upstream slope is increased,and the failure probability of downstream slope is dramatically reduced.The safety factor and failure probability of dam after reinforcement meet standard requirements,which shows that the reinforcement measures adopted are reliable and effective.

    参考文献
    相似文献
    引证文献
引用本文

徐 宇.某土石坝加固前后渗流及坝坡稳定性对比分析[J].江西水利科技,2018,(6):

复制
分享
文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:
  • 最后修改日期:
  • 录用日期:
  • 在线发布日期: 2019-02-26
  • 出版日期:
文章二维码