Analysis on the backwater effect of water storage in Xiajiang Hydro-junction Project on Ji’an Hydrological Station
Author:
Affiliation:

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    受赣江峡江水利枢纽工程蓄水影响,上游吉安水文站水位受顶托影响严重,水文规律被扰乱.收集2010~2016年吉安水文站、2015~2016年峡江水利枢纽工程的水文资料,分析了峡江水利枢纽工程初期蓄水对吉安水文站水位的顶托影响,得出峡江水利枢纽工程在较低水位且吉安站流量较小时,吉安站水位受顶托较为明显的结论.

    Abstract:

    Affected by the impoundment of Xiajiang Hydro-junction Project,the upper reaches of Ji’an hydrological station were seriously affected by the top-pounding and the hydrological laws were disrupted.The hydrological data of Ji’an hydrological stations(2010-2016)and Xiajiang Hydro-junction Project(2015-2016)were collected.The impact of the initial impoundment of the Xiajiang Hydro-junction Project on the water level of the Ji’an Hydrological Station was analyzed.At the lower water level,Ji’an station traffic is small,the water level of Ji’an station was jacked by the more obvious conclusion was drown.

    参考文献
    相似文献
    引证文献
引用本文

刘 斌.峡江水利枢纽工程蓄水对吉安水文站顶托影响分析[J].江西水利科技,2018,(1):63-66

复制
分享
文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:
  • 最后修改日期:
  • 录用日期:
  • 在线发布日期: 2018-04-26
  • 出版日期:
文章二维码