峡江水利枢纽二期工程2012年施工度汛措施
DOI:
作者:
作者单位:

作者简介:

通讯作者:

中图分类号:

TV87

基金项目:


The Second-stage Phase of Xiajiang Key Water-control Project 2012 Construction Action in flood season
Author:
Affiliation:

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    2012年峡江水利枢纽二期工程因船闸基础断层处理进度滞后,影响施工度汛。通过采取积极措施应对,确保了2次大洪水施工安全度汛,避免了重大损失,节点目标和总工期计划未受影响。本文对峡江水利枢纽二期工程2012年施工度汛措施进行了介绍,为今后类似情况作参考

    Abstract:

    Xiajiang Key Water-control Project in 2012 is at the construction peak,but the progress of the second-stage phase lagged due to the processing of ship lock base fault affects construction and flood prevention.By taking positive action,we ensured the construction safety in the great flood season twice and avoided significant loss.The goal of node and the total time limit for project is not affected.This article introduces the action of 2012 second stage of Xiajiang Key Water-control Project construction action in flood season.

    参考文献
    相似文献
    引证文献
引用本文

朱爱如.峡江水利枢纽二期工程2012年施工度汛措施[J].江西水利科技,2015,(1):74-77

复制
分享
文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:
  • 最后修改日期:
  • 录用日期:
  • 在线发布日期: 2015-07-03
  • 出版日期:
文章二维码