朱爱如.江西省峡江水利枢纽船闸闸室设计变更方案选择[J].江西水利科技,2015,(2):109-112
江西省峡江水利枢纽船闸闸室设计变更方案选择
Introduction of changing the ship lock chamber design for Xiajiang Water Control Project
  
DOI:
中文关键词: 船闸  整体式结构  设计方案  峡江水利枢纽工程
英文关键词: Ship lock  Integrated structure  Design  Xiajiang Water Control Project
基金项目:
作者单位
朱爱如 江西省峡江水利枢纽工程管理局 
摘要点击次数: 707
全文下载次数: 709
中文摘要:
      江西省峡江水利枢纽船闸6#~10#闸室段地基开挖后揭露地质条件变化较大,地质断层范围扩大。原设计采用分离式闸室结构方案已不适用,必须进行设计方案变更。经比较后,变更方案采用整体式结构设计,较好地解决了地质断层对闸室结构稳定的影响,保证了船闸结构的安全。
英文摘要:
      Because of the great change of exposed geological condition and the expansion of geological faults range beneath 6#-10# lock chambers of Xiajiang Water Control Project after its base excavation,the original design of seperated lock chambers structure has been inappropriate.The design has to be altered.By comparison,the inergrated struture design is chosen as the final edition.This design can minimize the effect of geological faults to the stability of lock chamber structure and ensure the safety of chamber structure.
查看全文   查看/发表评论  下载PDF阅读器
关闭